Informing Stakeholders

A schedule update is distributed regularly to provide project stakeholders with an assessment of the progress of the project against the master schedule. This updated schedule is called the current schedule. The current schedule provides new start and end dates for all activities and the project. Calculations based on the current schedule may result in a new critical path and subsequent changes in the project execution plan.

The project team develops an understanding of the project productivity by comparing the current schedule to the original schedule. If the schedule is behind original estimates, the project team conducts an assessment of the causes of the schedule slippage and develops a plan to address the changes to the project. The project management team typically has several alternatives for addressing changes to the project situation. Selecting the right alternative requires good information.

Callback before_footer in local_aigrade component should be migrated to new hook callback for core\hook\output\before_footer_html_generation
  • line 7225 of /lib/moodlelib.php: call to debugging()
  • line 7292 of /lib/moodlelib.php: call to {closure}()
  • line 71 of /lib/classes/hook/output/before_footer_html_generation.php: call to get_plugins_with_function()
  • line 987 of /lib/classes/output/core_renderer.php: call to core\hook\output\before_footer_html_generation->process_legacy_callbacks()
  • line 154 of /mod/book/view.php: call to core\output\core_renderer->footer()